Work Profile Report [125W322]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : शासनादेश संख्या 1500(1)/।।।(2)/ 20-12(प्रा0आ0)/2017 दिनांक 04.09.2020
TS Amount (lakhs) : 9.99 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
9.99
Resanction Cost :
9.99
Tentative Cost :
9.99
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
9.89
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.10
Work completed
Sanction on : 7 years 2 weeks ago
17 Dec 2018
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
0 %
Tentative Completion date on : 1 year 2 months from now
31 Mar 2027
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कास्तकारों के क्षेत्र से बाहर होने के कारण मुआवजा वितरण में कठिनाई हो रही है। -- as on 29-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: