Work Profile Report [125W374]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश संख्या 3579(1)/।।।(2)/21-39(एम0एल0ए0)/2017टी0सी0-3 दिनांक 10.09.2021
TS Amount (lakhs) : 303.1 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
303.10
Resanction Cost :
314.86
Tentative Cost :
303.10
Saving
11.76
Exp. Upto Last Fy :
302.96
For CFY 2024-2025
Remaining :
11.90
Demand :
2.00
Allotment :
11.90
Exp in CFY :
1.13
Total Up to Date Exp :
304.09
In Maintenance After Completion
Sanction on : 3 years 3 months ago
10 Sep 2021
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 8 months ago
22 Apr 2023
Actual Completion Date : 1 year 8 months ago
22 Apr 2023
Physical Linear Components
Remark
कार्य पूर्ण। मार्ग अनुरक्षण अवधि में है। -- as on 08-Nov-2023