Work Profile Report [125W498]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 38360/2023 ई पत्रावली संख्या 48456 दिनांक 14.07.2023
TS Amount (lakhs) : 76.1 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
76.10
Resanction Cost :
76.10
Tentative Cost :
76.10
Exp. Upto Last Fy :
64.60
For CFY 2024-2025
Remaining :
11.50
Demand :
11.50
Allotment :
8.43
Exp in CFY :
8.43
Total Up to Date Exp :
73.03
Work completed
Sanction on : 1 year 5 months ago
14 Jul 2023
Physical Progress:
At start of FY 2024-2025 :
90 %
Up to Date :
100 %
Tentative Completion date on : 1 month 3 weeks ago
31 Oct 2024
Actual Completion Date : 1 year 1 month ago
25 Nov 2023
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 13-Dec-2024
Assets :
Work not linked with IM