Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.1 | 2.1 | 4.200 | -2.1 | 4.200 | 4.200 |
125W504 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 45543/2023 ई पत्रावली संख्या 48456 दिनांक 31.07.2023
TS Amount (lakhs) : 24.93 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
24.93
Resanction Cost :
24.93
Tentative Cost :
24.93
Exp. Upto Last Fy : 20.11
For CFY 2024-2025
Remaining : 4.82
Demand : 4.82
Allotment : 4.49
Exp in CFY : 0.63
Total Up to Date Exp : 20.74
Work completed
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 100 %
Sanction on :
11 months 2 weeks ago
31 Jul 2023
Tentative Completion date:
1 month 3 weeks ago
26 May 2024
Actual Completion Date:
2 months 3 weeks ago
20 Apr 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व अवशेष। -- as on 27-Oct-2023