Work Profile Report [125W507]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : जिलाधिकारी गढवाल के पत्रांक सं0 306/09-प्रशा0अधि0 नजारत/2022-24 दिनांक 01.05.2023
TS Amount (lakhs) : 75.61 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
75.61
Resanction Cost :
80.00
Tentative Cost :
80.00
Exp. Upto Last Fy :
79.81
For CFY 2025-2026
Remaining :
0.19
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
79.81
Work completed
Sanction on : 2 years 2 months ago
01 May 2023
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 4 months 2 weeks ago
20 Feb 2025
Actual Completion Date : 1 year 19 hours ago
08 Jul 2024
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 23-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: