Work Profile Report [125W533]

वित्तीय वर्ष 2023-24 के अन्तर्गत पैठाणी बडेथ मोटर मार्ग के कि0मी0 08 में स्कपर निर्माण कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

Administrative Approval Detail : ।/122992/2023 इ्र0 पत्रावली सं0 52991 दिनांक 18.05.2023

TS Amount (lakhs) : 2.47 Lacs

Budget Financial Head : SRMD ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

2.47

Resanction Cost :

2.47

Tentative Cost :

2.47

Exp. Upto Last Fy :

0.00

For CFY 2024-2025

Remaining :

2.47

Demand :

2.47

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

0.00

Work completed

Sanction on : 1 year 2 months ago

18 May 2023

Physical Progress:

At start of FY 2024-2025 :

80 %

Up to Date :

10 %

Tentative Completion date on : 7 months 2 weeks from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Jobs
1
1
1
-

Remark

view all

कार्य पूर्ण। -- as on 02-May-2024

Rating : 172

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: