Work Profile Report [125W540]

मजरा महादेव से सुनारगांव इण्टर लाॅकिग टाइल्स का कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks

    Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : जिलाधिकारी गढवाल के पत्रांक 434/09-प्राशा0अधि0 नजारतध्2023-24 दिनांक 29.02.2024

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : SRMD ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

9.00

Resanction Cost :

9.00

Tentative Cost :

9.00

Exp. Upto Last Fy :

0.00

For CFY 2024-2025

Remaining :

9.00

Demand :

9.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

0.00

Construction Started

Sanction on : 8 months 3 weeks ago

29 Feb 2024

Physical Progress:

At start of FY 2024-2025 :

0 %

Up to Date :

50 %

Tentative Completion date on : 4 months 1 week from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Jobs
1
1
1
-

Remark

view all

कार्य प्रगति पर। -- as on 02-May-2024

Rating : 105

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand