Work Profile Report [125W585]

थैलीसैण चैरीखाल चिपलघाट मोटर मार्ग राज्य मार्ग संख्या 02।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks

    Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0सं0 191/14याता0(क)-उ0/2023 दिनांक 09.02.2024

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : SRMD ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

232.75

Resanction Cost :

232.75

Tentative Cost :

232.75

Exp. Upto Last Fy :

0.00

For CFY 2024-2025

Remaining :

232.75

Demand :

232.75

Allotment :

100.00

Exp in CFY :

0.00

Total Up to Date Exp :

0.00

Work completed

Sanction on : 7 months 1 week ago

09 Feb 2024

Physical Progress:

At start of FY 2024-2025 :

0 %

Up to Date :

0 %

Tentative Completion date on : 1 year 1 month from now

31 Oct 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
13
13
0.000
13
13.000
0.000

Remark

view all

कार्य प्रगति पर। -- as on 20-May-2024

Rating : 0

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: