Work Profile Report : 125W621
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : E patrawali No 26505
TS Amount (lakhs) : 35.22 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
35.22
Resanction Cost :
35.22
Tentative Cost :
35.22
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
35.22
Demand :
25.00
Allotment :
35.22
Exp in CFY :
7.36
Total Up to Date Exp :
7.36
Construction Started
Sanction on : 9 months 1 week ago
05 May 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
60 %
Tentative Completion date on : 1 year 1 month from now
31 Mar 2027
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
0.500 मी0 में पहाड कटान का कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 14-Jan-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: