Work Profile Report [126W197]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : सयुक्त सचिव, उत्तराखण्ड शासन के ई॰फाईल संख्या 67047/06 दि॰ 06.02.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Bridges State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
3.15
Resanction Cost :
3.15
Tentative Cost :
3.14
Saving
0.01
Exp. Upto Last Fy :
1.99
For CFY 2025-2026
Remaining :
1.16
Demand :
1.15
Allotment :
1.15
Exp in CFY :
1.15
Total Up to Date Exp :
3.14
Work completed
Sanction on : 1 year 10 months ago
06 Feb 2024
Physical Progress:
At start of FY 2025-2026 :
30 %
Up to Date :
100 %
Tentative Completion date on : 3 months 2 weeks from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 0.01 has been recorded as expected cost of work reduced from 3.15 to 3.14 . -- as on 10-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: