Work Profile Report [126W6]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : शासनादेश संख्या 5377/111 (2)/13-13 (मु.मं.घो.)/2012 दिनांक 14/01/2013
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
25.20
Resanction Cost :
25.20
Tentative Cost :
10.00
Saving
15.20
Exp. Upto Last Fy :
6.06
For CFY 2025-2026
Remaining :
19.14
Demand :
2.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
6.06
Work completed
Sanction on : 12 years 11 months ago
14 Jan 2013
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 10 months 1 week from now
30 Oct 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 15.2 has been recorded as expected cost of work reduced from 25.2 to 10.00 . -- as on 09-Dec-2025