Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3 | 0 |
126W97 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा॰सं॰ 5542/।।। (2)/18-06 (एम॰एल॰ए॰) /2017 टी॰सी॰ दिनांक 14.11.2018
TS Amount (lakhs) : 187.15 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
187.15
Resanction Cost :
187.15
Tentative Cost :
187.15
Exp. Upto Last Fy : 161.15
For CFY 2024-2025
Remaining : 26.00
Demand : 6.92
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 161.15
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
5 years 8 months ago
14 Nov 2018
Tentative Completion date:
3 years 3 months ago
31 Mar 2021
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। मुआवजा दायित्व शेष। -- as on 01-Sep-2022
Physical Peramenters