Work Profile

श्री केदारनाथ धाम परिक्षेत्रान्तर्गत प्रशासनिक कार्यालय व अस्पताल भवन का निर्माण कार्य (आर०ई०सी०)


Work not linked with IM

Roads on The Basis of AI: Road 1

Bridges on The Basis of AI: Garurchatti Bridge

Administrative Approval Detail : शासनादेश संख्या - 1440/VI(1)/2020-03(18)/2020

TS Amount (lakhs) : 1999.12 Lacs

Financial Detail (in Rs Lakhs)

Sanction Cost :

1999.12

Resanction Cost :

2265.16

Tentative Cost :

2265.16

Exp. Upto Last Fy : 927.38

For CFY 2024-2025

Remaining : 1,337.78

Demand : 0.00

Allotment : 0.00

Exp in CFY : 0.00

Total Up to Date Exp : 927.38

Construction Started

Physical Progress:

At start of FY 2024-2025 : 60 %

Up to Date : 60 %

Sanction on :
3 years 9 months ago
24 Sep 2020


Tentative Completion date:
1 year 7 months ago
04 Dec 2022


Actual Completion Date:
Not Yet Reported


Rating : 60

Remark

Bottelneck: no issue


Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Buildings 2 2 2 0
Currently only Bank Gaurantee information is avilable