Work Profile Report [127W11]
Remarks
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश संख्या - 1440/VI(1)/2020-03(18)/2020
TS Amount (lakhs) : 1999.12 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
1999.12
Resanction Cost :
2265.16
Tentative Cost :
2265.16
Exp. Upto Last Fy :
927.38
For CFY 2024-2025
Remaining :
1,337.78
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
927.38
Construction Started
Sanction on : 4 years 2 months ago
24 Sep 2020
Physical Progress:
At start of FY 2024-2025 :
60 %
Up to Date :
60 %
Tentative Completion date on : 1 year 11 months ago
04 Dec 2022
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Assets :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: Garurchatti Bridge