Work Profile Report [128W112]

fवकासखण्ड पोखरी के अन्तर्गत रा0इ0का0 चैण्डी से fवरसण सेरा तक मोटर मार्ग का नव fनर्माण का कार्य (प्रथम चरण)
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

Administrative Approval Detail : शा0 सं0 3278/।।।(2)/17-04(एम0एल0ए0)/2015 दिं0 03.01.2017

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

42.62

Resanction Cost :

42.62

Tentative Cost :

42.62

Exp. Upto Last Fy :

0.48

For CFY 2024-2025

Remaining :

42.14

Demand :

0.50

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

0.48

Alignment Approved

Sanction on : 7 years 7 months ago

03 Jan 2017

Physical Progress:

At start of FY 2024-2025 :

60 %

Up to Date :

60 %

Tentative Completion date on : 7 months 2 weeks from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
5
5
0.000
5
0.000
0.000

Remark

view all

Overall Saving 2.02 has been recorded as expected cost of work reduced from 42.62 to 40.60 . -- as on 31-Jul-2024

Rating : 71

Forest Case Pending At : 13: AIP DFO

Hindrance / Bottleneck : Long Term Forest Approval

Assets :

Work not linked with IM

Bridges on The Basis of AI: