Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 4.000 | 0 | 0.000 | 0.000 |
128W140 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शां0सं0 1308ए/।।।(2)/19-04(एम0एल0ए0)/ 2017टी.सी.।। दिनांक 08.03.2019।
TS Amount (lakhs) : 266.41 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
266.41
Resanction Cost :
266.41
Tentative Cost :
266.41
Exp. Upto Last Fy : 264.00
For CFY 2024-2025
Remaining : 2.41
Demand : 7.00
Allotment : 7.00
Exp in CFY : 0.00
Total Up to Date Exp : 264.00
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
5 years 4 months ago
08 Mar 2019
Tentative Completion date:
2 years 3 months ago
31 Mar 2022
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। अनुरक्षण मद के अन्तर्गत कार्य किया जाना है। -- as on 15-Jul-2024
Physical Peramenters