Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 16 | 16 | 0.000 | 16 | 0.000 | 0.000 |
128W250 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या 4088/।।।(2)/2023-(प्रा0आ0)/2023 दिनांक 01.11.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
81.58
Resanction Cost :
81.58
Tentative Cost :
81.58
Exp. Upto Last Fy : 45.47
For CFY 2024-2025
Remaining : 36.11
Demand : 36.11
Allotment : 35.00
Exp in CFY : 0.00
Total Up to Date Exp : 45.47
Construction Started
Physical Progress:
At start of FY 2024-2025 : 55 %
Up to Date : 60 %
Sanction on :
8 months 2 weeks ago
01 Nov 2023
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति में। -- as on 02-Mar-2024