Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6 | 2 | 2.000 | 0 | 0.000 | 0.000 |
128W86 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0ः-2755/।।।-2/06-52(प्रा0आ0)/06 दिनांक 10.11.2006
TS Amount (lakhs) : 100.8 Lacs
Financial Detail
Sanction Cost : 100.80 Lacs
Resanction Cost : 100.80 Lacs
Exp. Upto Last Fy : 97.66 Lacs
For CFY 2024-2025
Remaining : 3.14 Lacs
Demand : 0.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 97.66 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
17 years 6 months ago
10 Nov 2006
Tentative Completion date:
2 years 1 month ago
31 Mar 2022
Actual Completion Date:
2 years 7 months ago
04 Oct 2021
Remark
Forest Status 18: Final Approval
Bottelneck: no issue
2.00 कि0मी0 में कार्य पूर्ण। अवशेष लम्बाई में पुनरीक्षित आगणन गठन की कार्यवाही की जा रही है। -- as on 16-Apr-2024
Physical Peramenters