Work Profile Report [129W532]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : श्शा0सं0 931/।।।(2)/20-33(एम.एल.ए.)2017टीसीआई दिनांक 30.03.2021
TS Amount (lakhs) : 88.76 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
88.76
Resanction Cost :
88.76
Tentative Cost :
60.00
Saving
28.76
Exp. Upto Last Fy :
52.43
For CFY 2024-2025
Remaining :
36.33
Demand :
10.33
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
52.43
In Maintenance After Completion
Sanction on : 3 years 7 months ago
30 Mar 2021
Physical Progress:
At start of FY 2024-2025 :
70 %
Up to Date :
100 %
Tentative Completion date on : 8 months 1 week ago
15 Mar 2024
Actual Completion Date : 6 months 3 weeks ago
30 Apr 2024
Physical Linear Components
Remark
Overall Saving 28.76 has been recorded as expected cost of work reduced from 88.76 to 60.00 . Due to Tender Below Rate. -- as on 06-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand