Work Profile Report [129W660]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : उत्तराखण्ड शासनादेश ई फाईल सं0-51297, लोक निर्माण अनुभाग-2 दिनांक 28.03.2023
TS Amount (lakhs) : 53.08 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
53.08
Resanction Cost :
53.08
Tentative Cost :
45.00
Saving
8.08
Exp. Upto Last Fy :
53.08
For CFY 2025-2026
Remaining :
0.00
Demand :
0.80
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
53.08
In Maintenance After Completion
Sanction on : 2 years 5 months ago
28 Mar 2023
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 7 months ago
30 Dec 2023
Actual Completion Date : 1 year 7 months ago
30 Dec 2023
Physical Linear Components
Remark
दिनांक 30.12.2023 को कार्य पूर्ण । उक्त कार्य में 5 वर्षीय अनुरक्षण हेतु निर्धारित हैI -- as on 14-Aug-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: