Work Profile Report [129W685]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : शासनादेश ई-फाईल सं0-48594, दिनांक 19.07.2023, लोक निर्माण अनुभाग-2, उत्तराखण्ड
TS Amount (lakhs) : 54.11 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
54.11
Resanction Cost :
54.11
Tentative Cost :
42.00
Saving
12.11
Exp. Upto Last Fy :
15.00
For CFY 2024-2025
Remaining :
39.11
Demand :
27.00
Allotment :
22.00
Exp in CFY :
10.22
Total Up to Date Exp :
25.22
Construction Started
Sanction on : 1 year 4 weeks ago
19 Jul 2023
Physical Progress:
At start of FY 2024-2025 :
30 %
Up to Date :
80 %
Tentative Completion date on : 1 month 1 week from now
30 Sep 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 12.11 has been recorded as expected cost of work reduced from 54.11 to 42 . Due to Below Tender Rate. -- as on 01-Aug-2024