Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.3 | 1.3 | 0.700 | 0.6 | 0.600 | 0.600 |
129W686 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश ई-फाईल सं0-46134, दिनांक 31.07.2023, लोक निर्माण अनुभाग-2, उत्तराखण्ड
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
58.37
Resanction Cost :
62.75
Tentative Cost :
62.75
Exp. Upto Last Fy : 32.55
For CFY 2024-2025
Remaining : 30.20
Demand : 0.17
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 32.55
Work completed
Physical Progress:
At start of FY 2024-2025 : 45 %
Up to Date : 100 %
Sanction on :
11 months 2 weeks ago
31 Jul 2023
Tentative Completion date:
2 months 1 week ago
06 May 2024
Actual Completion Date:
4 weeks 1 day ago
18 Jun 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। 18.06.2024 -- as on 18-Jun-2024
Physical Peramenters