Work Profile Report [129W689]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश ई-फाईल सं0-46134, दिनांक 31.07.2023, लोक निर्माण अनुभाग-2, उत्तराखण्ड
TS Amount (lakhs) : 39.93 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
39.93
Resanction Cost :
39.93
Tentative Cost :
30.11
Saving
9.82
Exp. Upto Last Fy :
0.11
For CFY 2024-2025
Remaining :
39.82
Demand :
30.00
Allotment :
23.00
Exp in CFY :
26.20
Total Up to Date Exp :
26.31
Work completed
Sanction on : 1 year 3 months ago
31 Jul 2023
Physical Progress:
At start of FY 2024-2025 :
15 %
Up to Date :
100 %
Tentative Completion date on : 6 months 2 weeks ago
06 May 2024
Actual Completion Date : 4 months 3 weeks ago
29 Jun 2024
Physical Linear Components
Remark
Overall Saving 9.82 has been recorded as expected cost of work reduced from 39.93 to 30.11 . Due to Below Tender Rate. -- as on 01-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: