Work Profile Report [129W708]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश ई-फाईल सं0-46134, लोक निर्माण अनुभाग-2 उत्तराखण्ड, दिनांक 26.09.2023
TS Amount (lakhs) : 12 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
12.00
Resanction Cost :
12.00
Tentative Cost :
7.00
Saving
5.00
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
12.00
Demand :
7.00
Allotment :
7.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Survey work done
Sanction on : 1 year 2 months ago
26 Sep 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
50 %
Tentative Completion date on : 4 months 3 days from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 5 has been recorded as expected cost of work reduced from 12 to 7 . Due to Below Tender Rate. -- as on 01-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand