Work Profile Report [129W713]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : लोक निर्माण अनुभाग-2, उत्तराखण्ड शासनादेश ई फाईल सं0-54552, दिनांक 22.11.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
18.00
Resanction Cost :
18.00
Tentative Cost :
18.00
Exp. Upto Last Fy :
13.45
For CFY 2024-2025
Remaining :
4.55
Demand :
4.55
Allotment :
4.55
Exp in CFY :
4.10
Total Up to Date Exp :
17.55
Work completed
Sanction on : 8 months 3 weeks ago
22 Nov 2023
Physical Progress:
At start of FY 2024-2025 :
10 %
Up to Date :
100 %
Tentative Completion date on : 2 weeks 5 days ago
28 Jul 2024
Actual Completion Date : 2 months 2 weeks ago
30 May 2024
Physical Linear Components
Remark
कार्य पूर्ण। दायित्व शेष। -- as on 01-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand