Work Profile Report [129W731]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : उत्तराखण्ड शासनादेश ई-फाईल सं0-49430 , लोक निर्माण अनुभाग-2, दिनांक 29.11.2023
TS Amount (lakhs) : 53.85 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
53.85
Resanction Cost :
53.85
Tentative Cost :
49.81
Saving
4.04
Exp. Upto Last Fy :
23.81
For CFY 2024-2025
Remaining :
30.04
Demand :
26.00
Allotment :
26.00
Exp in CFY :
30.02
Total Up to Date Exp :
53.83
Work completed
Sanction on : 11 months 3 weeks ago
29 Nov 2023
Physical Progress:
At start of FY 2024-2025 :
25 %
Up to Date :
100 %
Tentative Completion date on : 3 months 4 days ago
19 Aug 2024
Actual Completion Date : 5 months 3 weeks ago
30 May 2024
Physical Linear Components
Remark
Overall Saving 4.04 has been recorded as expected cost of work reduced from 53.85 to 49.81 . Due to Below Tender Rate. -- as on 01-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: