Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.3 | 1.3 | 0.500 | 0.8 | 0.800 | 0.800 |
129W734 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासनादेश ई-फाईल सं0-49430 , लोक निर्माण अनुभाग-2, दिनांक 29.11.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
66.64
Resanction Cost :
66.64
Tentative Cost :
66.64
Exp. Upto Last Fy : 18.10
For CFY 2024-2025
Remaining : 48.54
Demand : 38.00
Allotment : 23.63
Exp in CFY : 23.63
Total Up to Date Exp : 41.73
Work completed
Physical Progress:
At start of FY 2024-2025 : 45 %
Up to Date : 100 %
Sanction on :
7 months 2 weeks ago
29 Nov 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
1 month 2 weeks ago
30 May 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 01-Jun-2024
Physical Peramenters