Work Profile Report [129W812]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : उत्तराखण्ड शासन की ई-फाईल सं0-53493/32, लोक निर्माण अनुभाग-2, दिनांक 05.08.2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
42.30
Resanction Cost :
42.30
Tentative Cost :
42.30
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
42.30
Demand :
5.00
Allotment :
0.66
Exp in CFY :
0.66
Total Up to Date Exp :
0.66
Construction Started
Sanction on : 2 months 4 weeks ago
05 Aug 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
30 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 03-Nov-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: