Work Profile Report : 129W826
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : उत्तराखण्ड शासन की ई-फाईल सं0-53493/32, लोक निर्माण अनुभाग-2, दिनांक 21.10.2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
42.85
Resanction Cost :
42.85
Tentative Cost :
42.85
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
42.85
Demand :
0.00
Allotment :
40.00
Exp in CFY :
18.08
Total Up to Date Exp :
18.08
Construction Started
Sanction on : 3 months 3 weeks ago
21 Oct 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
0 %
Tentative Completion date on : 1 month 2 weeks from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य गतिमान। -- as on 27-Jan-2026
Assets :
Work not linked with IM
Bridges on The Basis of AI: