Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 4 | 0 |
12W117 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 5150 / ।।। -(2) /10-18 (प्रा0आ0) / 2010 दिनांक 16.08.2010
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 50.40 Lacs
Resanction Cost : 50.40 Lacs
Exp. Upto Last Fy : 2.66 Lacs
For CFY 2024-2025
Remaining : 47.74 Lacs
Demand : 1.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 2.66 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 26 %
Up to Date : 26 %
Sanction on :
13 years 8 months ago
16 Aug 2010
Tentative Completion date:
2 years 4 months ago
30 Dec 2021
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 02: Division
Bottelneck: no issue
डिजिटल मानचित्र दि0 29/04/2024 को तैयार कर लिये गये है।वन अभ्यारण्य से दुरी का प्रमाण पत्र प्राप्त करने हेतु दि0 29/02/2024 तथा दि0 22/04/2024 को प्रभागीय वनाधिकारी देहरादून को पत्र लिखा गया है। माह मार्च में इस हेतु निर्धारित शुल्क भी जमा कर दिया है। प्रमाण् पत्र अपेक्षित है। -- as on 30-Apr-2024
Physical Peramenters