Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5.000 | 0 | 0.000 | 0.000 |
12W400 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 5068/।।।(2)/18-57(एम0एल0ए0)/2017 टी0सी0 लो0नि0-अनु0 2 दिनांक 15.10.2018
TS Amount (lakhs) : 316.67 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
316.67
Resanction Cost :
316.67
Tentative Cost :
316.67
Exp. Upto Last Fy : 226.33
For CFY 2024-2025
Remaining : 90.34
Demand : 15.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 226.33
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
5 years 9 months ago
15 Oct 2018
Tentative Completion date:
2 years 2 weeks ago
30 Jun 2022
Actual Completion Date:
3 months 2 weeks ago
31 Mar 2024
Remark
Bottelneck: no issue
निर्माण कार्य पूर्ण। अनुरक्षण कार्य प्रगति पर। -- as on 05-Jul-2024
Physical Peramenters