Work Profile Report [12W401]
Tenders
Project Activities
Samples
Administrative Approval Detail : शासनादेश सं0 8118/।।।(2)/18-16(प्रा0आ0)/2004 टी0सी0-1 दिनांक 28.12.2018
TS Amount (lakhs) : 363.1 Lacs
Budget Financial Head : SCSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
83.40
Resanction Cost :
363.10
Tentative Cost :
363.10
Exp. Upto Last Fy :
283.14
For CFY 2025-2026
Remaining :
79.96
Demand :
79.96
Allotment :
79.96
Exp in CFY :
79.96
Total Up to Date Exp :
363.10
Work completed
Sanction on : 6 years 11 months ago
28 Dec 2018
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 3 years 8 months ago
31 Mar 2022
Actual Completion Date : 2 years 7 months ago
21 Apr 2023
Physical Linear Components
Remark
कार्य पूर्ण। प्रतिकर भुगतान की कार्यवाही पूर्ण। -- as on 02-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: