Work Profile Report [12W401]
Tenders
Project Activities
Documents
Samples
Administrative Approval Detail : शासनादेश सं0 8118/।।।(2)/18-16(प्रा0आ0)/2004 टी0सी0-1 दिनांक 28.12.2018
TS Amount (lakhs) : 363.1 Lacs
Budget Financial Head : SCSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
83.40
Resanction Cost :
363.10
Tentative Cost :
363.10
Exp. Upto Last Fy :
239.97
For CFY 2024-2025
Remaining :
123.13
Demand :
123.00
Allotment :
46.00
Exp in CFY :
0.00
Total Up to Date Exp :
239.97
Work completed
Sanction on : 5 years 11 months ago
28 Dec 2018
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 2 years 8 months ago
31 Mar 2022
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
09/2020 में कार्य पूर्ण मुआवजा भुगतान शेष।मुआवजा भुगतान हेतु प्रपत्र तैयार किये जा रहे हैं। -- as on 15-Sep-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI: