Work Profile Report [12W426]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : शासनादेश सं0 560/।।। (2)/20-57 (एम0एल0ए0)/2017 टी0स्ी01 दिनांक 06.02.2020
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
64.85
Resanction Cost :
64.85
Tentative Cost :
64.85
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
64.85
Demand :
64.85
Allotment :
3.43
Exp in CFY :
3.43
Total Up to Date Exp :
3.43
Construction Started
Sanction on : 5 years 6 months ago
06 Feb 2020
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
10 %
Tentative Completion date on : 3 months 3 weeks from now
30 Nov 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
वन भूमि प्रस्ताव भारत सरकार स्तर पर विचाराधीन। -- as on 05-Aug-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: