Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Buildings | 1 | 1 | 1 | 0 | 0 | 1 |
12W443 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 442(1)/XXXVI(2)/2021-41-दो(8)/17
TS Amount (lakhs) : 165.71 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
165.71
Resanction Cost :
165.71
Tentative Cost :
165.71
Exp. Upto Last Fy : 119.97
For CFY 2024-2025
Remaining : 45.74
Demand : 12.00
Allotment : 12.31
Exp in CFY : 12.31
Total Up to Date Exp : 132.28
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
3 years 1 month ago
14 Jun 2021
Tentative Completion date:
6 months 2 weeks ago
30 Dec 2023
Actual Completion Date:
4 months 2 weeks ago
29 Feb 2024
Remark
Bottelneck: no issue
Work Complete. -- as on 08-Apr-2024
Physical Peramenters