Work Profile Report [12W452]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश सं0 3610 (1) /।।। (2)/21-57 (एम0एल0ए0)/2017 दिनांक 14.09.2021
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
7.50
Resanction Cost :
7.50
Tentative Cost :
7.50
Exp. Upto Last Fy :
1.73
For CFY 2024-2025
Remaining :
5.77
Demand :
0.10
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
1.73
Construction Started
Sanction on : 3 years 3 months ago
14 Sep 2021
Physical Progress:
At start of FY 2024-2025 :
23 %
Up to Date :
23 %
Tentative Completion date on : 2 months 2 weeks from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
हवाई दूरी प्रमाण पत्र प्राप्त। प्रस्ताव गठन की कार्यवाही गतिमान। -- as on 03-Jan-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand