Work Profile Report [12W486]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ई-फाईल सं0 48226 लोक निर्माण अनुभाग-2 देहरादून दिनांक 17.05.2023
TS Amount (lakhs) : 60.67 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
60.67
Resanction Cost :
60.67
Tentative Cost :
60.67
Exp. Upto Last Fy :
35.83
For CFY 2024-2025
Remaining :
24.84
Demand :
20.00
Allotment :
20.00
Exp in CFY :
10.00
Total Up to Date Exp :
45.84
Construction Started
Sanction on : 1 year 7 months ago
17 May 2023
Physical Progress:
At start of FY 2024-2025 :
80 %
Up to Date :
95 %
Tentative Completion date on : 3 months 1 week ago
15 Sep 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 05-Oct-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI: