Work Profile Report [12W494]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : उत्तराखण्ड शासन लोक निर्माण अनुभाग-2, सं0 1450/।।। (2)/23-03 (सामान्य) 2023 देहरादून दिनांक 02.05.2023
TS Amount (lakhs) : 148.2 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
148.20
Resanction Cost :
148.20
Tentative Cost :
141.00
Saving
7.20
Exp. Upto Last Fy :
117.76
For CFY 2024-2025
Remaining :
30.44
Demand :
30.44
Allotment :
20.00
Exp in CFY :
22.47
Total Up to Date Exp :
140.23
Work completed
Sanction on : 1 year 6 months ago
02 May 2023
Physical Progress:
At start of FY 2024-2025 :
25 %
Up to Date :
100 %
Tentative Completion date on : 6 months 2 days ago
21 May 2024
Actual Completion Date : 6 months 2 days ago
21 May 2024
Physical Linear Components
Remark
Overall Saving 7.2 has been recorded as expected cost of work reduced from 148.2 to 141 . -- as on 12-Sep-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand