Work Profile Report [12W498]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : संयुक्त सचिव, उत्तराखण्ड शासन के ई फॅाईल संख्या-48456 दिनांक 21.08.2023 द्वारा स्वीकृति प्राप्त।
TS Amount (lakhs) : 176.04 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
176.04
Resanction Cost :
176.04
Tentative Cost :
168.00
Saving
8.04
Exp. Upto Last Fy :
105.83
For CFY 2024-2025
Remaining :
70.21
Demand :
70.21
Allotment :
56.08
Exp in CFY :
56.08
Total Up to Date Exp :
161.91
Work completed
Sanction on : 1 year 4 months ago
21 Aug 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
100 %
Tentative Completion date on : 7 months 12 hours ago
25 May 2024
Actual Completion Date : 7 months 12 hours ago
25 May 2024
Physical Linear Components
Remark
Overall Saving 8.04 has been recorded as expected cost of work reduced from 176.04 to 168 . -- as on 12-Sep-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand