Administrative Approval Detail : ई0-56385 संख्या- 7349/।।। (2) /2024-01 (प्रा0आ0)/2023 लोक निर्माण अनुभाग-2 देहरादून दिनांक 06.11.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : सड़क सुरक्षा कार्य ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
16.38
Resanction Cost :
16.38
Tentative Cost :
16.38
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
16.38
Demand :
16.38
Allotment :
16.38
Exp in CFY :
14.43
Total Up to Date Exp :
14.43
Work completed
Sanction on : 11 months 4 weeks ago
06 Nov 2024
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
100 %
Tentative Completion date on : 6 months 2 weeks ago
14 Apr 2025
Actual Completion Date : 6 months 2 weeks ago
14 Apr 2025
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 19-May-2025