Work Profile Report [130W3]

widening of existing single lane road to 2 lane with paved shoulder configuration from km 235.00 to km 268.00 oh NH 58 including 560m marine drive viaduct portion near bypass in the state of uttarakhand under EPC mode
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan

  • Components
  • Forest

  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

  • Documents
  • Samples

Administrative Approval Detail : NH-58-UR-2016-17-477

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : SRMD ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

24822.00

Resanction Cost :

24822.00

Tentative Cost :

24822.00

Exp. Upto Last Fy :

16,156.64

For CFY 2024-2025

Remaining :

8,665.36

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

16,156.64

In Maintenance After Completion

Sanction on : 8 years 5 months ago

21 Sep 2016

Physical Progress:

At start of FY 2024-2025 :

100 %

Up to Date :

100 %

Tentative Completion date on : 3 years 7 months ago

28 Jul 2021

Actual Completion Date : 2 years 11 months ago

02 Apr 2022

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
30.59
30.59
30.59
-
Bridge
3 (127.1m)
3 (127.1m)
3 (127.1m)
-
Jobs
1
1
1
-

Remark

view all

चार धाम यात्रा के दृष्टिगत राजमार्ग अनुरक्षण के अन्तर्गत पैच मरम्मत, मलवा हटाने, क्षतिग्रस्त दीवारों की मरम्मत, नालियों की सफाई, क्षतिग्रस्त क्रैश बैरियर मरम्मत, क्षतिग्रस्त पैरपिटो की मरम्मत, झाडी कटान एवं अन्य मरम्मत कार्यो को करने हेतु खण्ड के पत्र संख्या 207/EPCII दिनांक 22.02.2025 द्वारा फर्म को पत्र प्रेषित किया गया। -- as on 24-Feb-2025

Rating : 100

Forest Case Pending At : 00: Not Started

No Hindrance / Bottleneck

Assets :

Road ID on IM : Road 1

Roads on The Basis of AI: Road 1 Road 2

Bridges on The Basis of AI: Malakunti Bridge Malakhunti bridge