Work Profile Report [131W12]
Forest
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : RO/UKlAnnual Plan/2022-23Rudraprayag/03 (Comp.213411)
TS Amount (lakhs) : 4743.37 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
4743.37
Resanction Cost :
4743.37
Tentative Cost :
4743.37
Exp. Upto Last Fy :
1,315.41
For CFY 2024-2025
Remaining :
3,427.96
Demand :
1,526.00
Allotment :
0.00
Exp in CFY :
1,165.06
Total Up to Date Exp :
2,480.47
Construction Started
Sanction on : 2 years 1 month ago
10 Oct 2022
Physical Progress:
At start of FY 2024-2025 :
55 %
Up to Date :
95 %
Tentative Completion date on : 6 months 4 days ago
23 May 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Sliding & Sinking zone treatment in progress -- as on 28-Mar-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: