Work Profile Report [131W16]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : RO/UK/AP/ 2022-23/Tunnel Revised Estimate (Comp. No.215054)
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Deposit ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
543.93
Resanction Cost :
543.93
Tentative Cost :
543.93
Exp. Upto Last Fy :
113.95
For CFY 2025-2026
Remaining :
429.98
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
113.95
Construction Started
Sanction on : 2 years 4 months ago
24 Feb 2023
Physical Progress:
At start of FY 2025-2026 :
25 %
Up to Date :
25 %
Tentative Completion date on : 7 months 1 week ago
21 Nov 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
work in progress. -- as on 17-Feb-2024