Work Profile Report [131W17]

वार्षिक योजना 2022-23 के अन्तर्गत रा0 मा0 संख्या 107ए के कि0 मी0 37 से 70 के मध्य मार्ग सुदृढ़ीकरण का कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : RO/UK/Annual Plan/ 2021-22/Rudraprayag/11 (Comp. No.217886)

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : SRMD ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

4241.25

Resanction Cost :

4241.25

Tentative Cost :

4241.25

Exp. Upto Last Fy :

734.73

For CFY 2024-2025

Remaining :

3,506.52

Demand :

2,523.00

Allotment :

0.00

Exp in CFY :

1,412.42

Total Up to Date Exp :

2,147.15

Construction Started

Sanction on : 1 year 9 months ago

08 Feb 2023

Physical Progress:

At start of FY 2024-2025 :

27 %

Up to Date :

70 %

Tentative Completion date on : 3 months 3 weeks from now

18 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
34
34
0.000
34
34.000
26.000

Remark

view all

Work in progress. -- as on 29-Sep-2023

Rating : 100

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand