Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.72 | 3.72 | 3.72 | 0 | ||
No of Bridges | 3 | 3 | 3 | 0 | ||
Span of Bridges [m] | 594.2 | 594.2 | 594.2 | 0 |
131W6 :
Administrative Approval Detail : एनएच -12014/48/2015-यू. आर./एनएच-II
TS Amount (lakhs) : 14802.1 Lacs
Financial Detail
Sanction Cost : 14,802.10 Lacs
Resanction Cost : 14,802.10 Lacs
Exp. Upto Last Fy : 6,128.91 Lacs
For CFY 2024-2025
Remaining : 8,673.19 Lacs
Demand : 0.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 6,128.91 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 42 %
Up to Date : 44 %
Sanction on :
8 years 6 months ago
18 Dec 2015
Tentative Completion date:
1 week 3 days ago
21 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
Work in progress. -- as on 27-Jul-2021
Physical Peramenters