Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 12.57 | 12.57 | 12.57 | 0 | ||
No of Bridges | 7 | 7 | 7 | 0 | ||
Span of Bridges [m] | 220 | 220 | 220 | 0 |
131W9 :
Work not linked with IM
Roads on The Basis of AI: Road 1 Road 2
Bridges on The Basis of AI: Devangana Bridge 55 m Kakragad Suspension Bridge
Administrative Approval Detail : आर0ओ0/यू0कके-12014/03/2017/एपी/एससीसी एंड एस एफ सी
TS Amount (lakhs) : 24800.3 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
24800.30
Resanction Cost :
24800.30
Tentative Cost :
24800.30
Exp. Upto Last Fy : 11,512.48
For CFY 2024-2025
Remaining : 13,287.82
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 11,512.48
Construction Started
Physical Progress:
At start of FY 2024-2025 : 64 %
Up to Date : 66 %
Sanction on :
6 years 4 months ago
26 Feb 2018
Tentative Completion date:
5 months 1 week from now
31 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 04: DFO
Bottelneck: Other Reason
Land Acquisition & Hindrance issues at few locations. -- as on 27-Jul-2021
Physical Peramenters