Work Profile Report [131W9]
Fin Plan
Tenders
Project Activities
Documents
Samples
Administrative Approval Detail : आर0ओ0/यू0कके-12014/03/2017/एपी/एससीसी एंड एस एफ सी
TS Amount (lakhs) : 24800.3 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
24800.30
Resanction Cost :
24800.30
Tentative Cost :
24800.30
Exp. Upto Last Fy :
11,512.48
For CFY 2024-2025
Remaining :
13,287.82
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
11,512.48
Construction Started
Sanction on : 6 years 10 months ago
26 Feb 2018
Physical Progress:
At start of FY 2024-2025 :
64 %
Up to Date :
66 %
Tentative Completion date on : 1 week 6 days ago
31 Dec 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Land Acquisition & Hindrance issues at few locations. -- as on 27-Jul-2021
Assets :
Work not linked with IM
Roads on The Basis of AI: Road 1 Road 2
Bridges on The Basis of AI: Devangana Bridge 55 m Kakragad Suspension Bridge RCC Solid slab Gaid