Work Profile Report [133W13]

ईपीसी मोड के तहत उत्तराखंड राज्य में किमी 168.605 से किमी 191.970 (नया एनएच-09) तक भूस्खलन क्षेत्र 11 स्थान का उपचार।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks

    Tenders

  • Aggrements
  • Project Activities

  • alerts
  • Documents

    Samples

Administrative Approval Detail : RO/UK/THDC/NH-09/2022-23/PKG-III

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : SRMD ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

5653.00

Resanction Cost :

5653.00

Tentative Cost :

5653.00

Exp. Upto Last Fy :

0.00

For CFY 2024-2025

Remaining :

5,653.00

Demand :

1,900.00

Allotment :

1,228.00

Exp in CFY :

1,228.00

Total Up to Date Exp :

1,228.00

Construction Started

Sanction on : 1 year 6 months ago

24 Feb 2023

Physical Progress:

At start of FY 2024-2025 :

0 %

Up to Date :

65 %

Tentative Completion date on : 6 months 1 week from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement

Remark

view all

Rating : 116

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand