Work Profile Report [133W13]
Remarks
Tenders
Project Activities
Documents
Samples
Administrative Approval Detail : RO/UK/THDC/NH-09/2022-23/PKG-III
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
5653.00
Resanction Cost :
5653.00
Tentative Cost :
5653.00
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
5,653.00
Demand :
1,900.00
Allotment :
1,228.00
Exp in CFY :
1,228.00
Total Up to Date Exp :
1,228.00
Construction Started
Sanction on : 1 year 10 months ago
24 Feb 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
65 %
Tentative Completion date on : 3 months 5 days from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Assets :
Work not linked with IM
Bridges on The Basis of AI: