Work Profile Report [139W3]
Tenders
Project Activities
Documents
Samples
Administrative Approval Detail : Government of India, Directorate General of works C.P.W.D., 433-B, A-wing, Nirman Bhawan, New Delhi (BFR Cell) vide letter no. DGW/BFR/32nd HLEC/2016-17/580 Dated 18-08-2016 for Rs. 252.81 crore.
TS Amount (lakhs) : 35101 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
25281.00
Resanction Cost :
30808.00
Tentative Cost :
30808.00
Exp. Upto Last Fy :
21,426.60
For CFY 2025-2026
Remaining :
9,381.40
Demand :
0.00
Allotment :
49.03
Exp in CFY :
0.00
Total Up to Date Exp :
21,426.60
Construction Started
Sanction on : 8 years 7 months ago
18 Aug 2016
Physical Progress:
At start of FY 2025-2026 :
85 %
Up to Date :
85 %
Tentative Completion date on : 3 months 1 week from now
25 Jul 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
work is executed in 3 no. of packages
Package I - Km 12.000- km 29.875 Work Completed
Package II - Km 30.565 - Km 55.000 Work Completed
Package III - 690 mtr bridge in Km 30 and 31 Work Start
-- as on 09-May-2024
Assets :
Work not linked with IM
Roads on The Basis of AI: Road 1 Road 2
Bridges on The Basis of AI: Steel girder bridge in km 1.00 at kakraligate thuligarh motor road Steel girder bridge in km 11.00 at kakraligate thuligarh motor road
© PWD Uttarakhand