Work Profile Report [140W10]

सी0एस0आर0 मद के अन्तर्गत Construction of Riverfront Development work (E1,E2) Under HPCL का निर्माण कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : 2340/VI(1)/2022-02(26)/2021

TS Amount (lakhs) : 5424 Lacs

Budget Financial Head : Deposit ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

2712.36

Resanction Cost :

2712.36

Tentative Cost :

2712.36

Exp. Upto Last Fy :

1,746.14

For CFY 2025-2026

Remaining :

966.22

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

1,746.14

Construction Started

Sanction on : 3 years 5 months ago

07 Jan 2022

Physical Progress:

At start of FY 2025-2026 :

47 %

Up to Date :

48 %

Tentative Completion date on : 6 months 1 week ago

30 Nov 2024

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement

Remark

view all

E1 LEFT ABUTMENT WALL BAR BINDING & CASTING WORK IN PROGRESS.
E2 LEFT ABUTMENT- EXCAVATION & CASEIN ERECTION IN PROGRESS.
-- as on 02-Jul-2024

Rating : 64

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: