Work Profile Report [140W13]

श्री बद्रीनाथ धाम में सी0एस0आर0 मद के अन्तर्गत श्री बद्रीनाथ धाम परिक्षेत्रान्तर्गत Riverfront Development work (G) Under IOCL CSR का निर्माण कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : 1993/VI(1)/2021-03(111)/2021

TS Amount (lakhs) : 2275.17 Lacs

Budget Financial Head : Deposit ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

2275.17

Resanction Cost :

2275.17

Tentative Cost :

2275.17

Exp. Upto Last Fy :

1,389.25

For CFY 2025-2026

Remaining :

885.92

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

1,389.25

Construction Started

Sanction on : 3 years 5 months ago

14 Dec 2021

Physical Progress:

At start of FY 2025-2026 :

69 %

Up to Date :

70 %

Tentative Completion date on : 8 months 1 week ago

30 Sep 2024

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement

Remark

view all

UPPER PROMENADE GABIAON WALL WORKS IN PROGRESS. -- as on 02-Jul-2024

Rating : 70

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: