Work Profile Report [140W14]
Tenders
Aggrements
Project Activities
alerts
Documents
Administrative Approval Detail : 6082/III(2)/21-04(M.L.A.)/2017T.C.II
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
3342.00
Resanction Cost :
3342.00
Tentative Cost :
3342.00
Exp. Upto Last Fy :
2,865.85
For CFY 2024-2025
Remaining :
476.15
Demand :
200.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
2,865.85
Construction Started
Sanction on : 2 years 8 months ago
15 Dec 2021
Physical Progress:
At start of FY 2024-2025 :
90 %
Up to Date :
90 %
Tentative Completion date on : 2 weeks 23 hours from now
31 Aug 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
अधिकांश काश्तकारों को प्रतिकर भुगतान कर दिया गया है। शेष कास्तकारों के प्रतिकर भुगतान की कार्यवाही गतिमान है। -- as on 13-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: