Work Profile Report [140W36]

श्री बद्रीनाथ धाम में दर्शन पंक्ति में पूर्व निर्मित रेन-शेल्टर के विस्तारीकरण का कार्य
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : ई पत्रावली संख्या - 35061/04

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

74.40

Resanction Cost :

74.40

Tentative Cost :

74.40

Exp. Upto Last Fy :

0.00

For CFY 2025-2026

Remaining :

74.40

Demand :

74.40

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

0.00

none

Sanction on : 2 months 1 week ago

27 Mar 2025

Physical Progress:

At start of FY 2025-2026 :

0 %

Up to Date :

60 %

Tentative Completion date on :

Yet To Decide

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
0.4
0.4
0.4
-

Remark

view all

-- as on 18-May-2025

Rating : 592

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: